  • If the knot is not in the correct position, flip the knot by giving a bit of a slack (1)
  • Make a loop (2)
  • Move it behind the sharp end of the rope (3)
  • Pull a bight of the rope belay end through the loop (4), making a slipknot around the sharp end
  • Grab the bight with a hand (5) and simultaneously take slack out of the system while releasing the other hand (6), note that the break strand is still always being held during this step
  • Pull the bight through the carabiner (7), increase its size if necessary for the next steps
  • Secure the tie-off...
  • ... by making an overhand around the life end of the rope (8,9)
  • And the mule-overhand tie-off is done